| + | ======Logbook====== | ||
| + | |||
| + | |||
| + | ===== Weekly Report ===== | ||
| + | |||
| + | ==== Week Report - 15.03-22.03 ==== | ||
| + | During this week, our team was searching for information connected with different approaches to solve the problem. We had team meetings and brainstorms about different solutions and ideas on how our fluid desinfection system should look like. | ||
| + | Our team also prepared a preliminary Gantt Chart with general tasks and timeline of our work till the final presentation. During this week we also had a meeting with the client and we obtained all the answers for our doubts and questions. After that we got a clear view of how our project should look like. | ||
| + | |||
| + | ==== Week Report - 22.03 -29.03 ==== | ||
| + | This week we had a meeting with António Ferreira da Silva to verify our hydraulic system and organized a meeting to develop the PC interface control system. We have been searching for equipment needed to build our project. We improved our marketing plan. We worked on the Interim Report. We organized four meetings to develop these tasks together. | ||
| + | ==== Week Report - 29.03 -05.04 ==== | ||
| + | This week our team was building theoretically electrical system and searching for the necessary components for its construction. We had two meetings to resolve this issue. | ||
| + | ==== Week Report - 05.04 -12.04 | ||
| + | In this week our main goal was to find appropriate equipment (filter, pump, UV lamp) to build the system and determine the spesifications of these equipment. | ||
| + | Also we started doing marketing plan for our system - segmentation, | ||
| + | In addition, we design the logo for our " | ||
| + | |||
| + | ==== Week Report - 12.04 - 19.04 ==== | ||
| + | |||
| + | During this week we prepared and assembled interim report which includes: abstract, introduction, | ||
| + | |||
| + | ==== Week Report - 19.04 - 03.05 ==== | ||
| + | |||
| + | During those two weeks, we researched local market for buying appropriate materials to build our system. We made preliminary list of materials and then after discussion with our client we made corrections and created final list of materials from local shops. | ||
| + | ==== Week Report - 03.05 -17.05 ==== | ||
| + | |||
| + | In those two weeks our group finally bought materials to construct the disinfection system. Also, the person responsible for water test carried out first preliminary test of contaminated water in chemical engineering departments with help of professor Maria Aurora Soares da Silva. We also arranged PLC system from electrical department and make an appointment with professor to make an electrical scheme of the system . | ||
| + | ==== Week Report - 17.05 -24.05 ==== | ||
| + | |||
| + | In this week, each member of the group started to work with writing final report. Adam was improving marketing program, Sander was creating state of the art, Aleksandra prepared correct abstract and Joanna changed introduction. Additionally, | ||
| + | |||
| + | ==== Week Report - 24.05 -31.05 ==== | ||
| + | |||
| + | During this week we prepared scheme of electrical circuit and arrange power supply from electrical engineering department. We started also to assemble electrical part of the system what involves connecting all inputs (water lever sensors and buttons) and outputs (electrical valve, UV lamp, pump). What is more, all team members were still working with the parts of report: functionalities and tests elaboration. | ||
| + | |||
| + | ==== Week Report - 31.05 -07.06 ==== | ||
| + | |||
| + | During this week, our group finished to assemble electrical part of the system and started to construct mechanical part. We also programmed our PLC to control all electrical equipments and made a simulation to make sure that the system will work properly. What`s more we prepared project development part for the final report. In the same time, we were recording our work and started to work on video and poster. | ||
| + | |||
| + | |||
| + | ==== Week Report - 07.06 - 14.06 ==== | ||
| + | |||
| + | In the last week before final presentation, | ||
| + | ===== Meetings ===== | ||
| + | ==== 1st Meeting | ||
| + | |||
| + | === Agenda: === | ||
| + | - Presentation | ||
| + | - Modus operandi | ||
| + | - Project proposal | ||
| + | - Electronic Logbook | ||
| + | |||
| + | === Minute: === | ||
| + | Getting familiar with the proposed themes and selection of the project and its possible implementation. | ||
| + | |||
| + | ==== 2nd Meeting (2011-03-08) ==== | ||
| + | === Agenda: === | ||
| + | - Where this disinfection system should be used? | ||
| + | - How big are the volumes of these fluids? | ||
| + | - Cycle times? | ||
| + | - How clean the fluid should be after disinfecting? | ||
| + | - What information should the PC/ | ||
| + | - Whether it should be possible to change something through the user interface? | ||
| + | - What equipments are available ? | ||
| + | - Do we know water properties? What kind of bacterias contains the water? | ||
| + | - Where the water come from? | ||
| + | - Where container will be used? | ||
| + | - What is the budget for this project? | ||
| + | |||
| + | === Minute: === | ||
| + | |||
| + | ---- | ||
| + | Date:__ **09.03.2012**__ | ||
| + | |||
| + | Present: All members of team 2, supervisors | ||
| + | |||
| + | The meeting was started from discussion and answering questions from agenda: | ||
| + | - Where this disinfection system should be used? The system will be used in a greenhouse nearby the entrance of the students car parking. It may be tested in the Laboratório de Tecnologia (Building L, room L101). | ||
| + | - How big are the volumes of these fluids? Think of 100 l/h. You should project the tank so shat this flowrate can be treated “continuously”. | ||
| + | - Cycle times? It may depend on the design. The system should be able of disinfecting/ | ||
| + | - What fluids are going to be disinfected? | ||
| + | - How clean the fluid should be after disinfecting? | ||
| + | - What information should the PC/ | ||
| + | - Whether it should be possible to change something through the user interface? The user may want to set the “flowrate” of the water through the system or choose between fresh water, brackish water or brine (seawater) in order to adjust the system. | ||
| + | |||
| + | Second part of the meeting was devoted to explain what kind of work our team is supposed to do for next project weekly meeting. We are supposed to prepare information of different approaches to solve given problem. It was suggested to propare table for each approach which will contain: way of dissinfection (UV, chemicals, biomaterials), | ||
| + | |||
| + | ==== 3d Meeting | ||
| + | === Agenda: === | ||
| + | - Discussion and presentation different methods of problem solving | ||
| + | - Choosing the best method | ||
| + | - Discussion about hydraulical and electrical equipment | ||
| + | |||
| + | ==== 4th Meeting | ||
| + | === Agenda: === | ||
| + | |||
| + | - Discussion and presentation of our system | ||
| + | - Automatical part of our system (discussion about using sensor to turn on/off the system) | ||
| + | - Discussion about list of material which we need to buy to build our system: | ||
| + | - Filter of 5 microns size: http:// | ||
| + | - UV lamps: http:// | ||
| + | |||
| + | ==== 5th Meeting | ||
| + | |||
| + | === Agenda: === | ||
| + | - presentation of alternative materials and providers, | ||
| + | - discussion of possibilities to choose alternative proposals, | ||
| + | - presentation of the implementation of the solution and final discussion of possible changes, | ||
| + | - questions about the type of tests required and needed for this material. | ||
| + | |||
| + | === Minute: === | ||
| + | |||
| + | Present: All group and supervisors | ||
| + | |||
| + | Meeting was started from presentation of list of materials for building our fluid disinfection system. All equipements and parts of the system are from PreçoFilters shop in Porto. All of them were accepted but the task of group is to provide and get know electrical specification of each part (current and voltage). After that we are supposed to decide if there is needed any voltage transformer. We also discussed how should look like troley/ | ||
| + | * professor Antonio Silva at 10 a.m on Wednesday (14.04) in order to prepare automation part of our system | ||
| + | * and our client in order to check what equipments in chamical laboratory are available for testing water. | ||
| + | |||
| + | ==== 8th Meeting | ||
| + | === Agenda: === | ||
| + | |||
| + | - Questions to Nídia Sá Caetano about the shopping procedures, | ||
| + | - Discussion with Nídia Sá Caetano about chemical bacteria water tests. | ||
| + | |||
| + | === Minute: === | ||
| + | During the meeting we got familiar with procedures of buying materials. After the meeting we went to chemical department and met with a person working with testing water. We saw laboratory and necessary equipment and make an appointment for the next day to carry out preliminary water test. | ||
| + | |||
| + | ==== 13th Meeting | ||
| + | === Agenda: === | ||
| + | * Final requirements | ||
| + | * Power supply (250 V -> 24 V) | ||
| + | ===== Activities ===== | ||
| + | |||
| + | ^ Start and End^ | ||
| + | |March| |Search components and materials on the Internet | ||
| + | |March| |Gantt Chart | Sander| | ||
| + | |March| |Project sketch | ||
| + | |March, April, May| |Search for providers and materials in stores | ||
| + | |April||Leaflet | ||
| + | |April||The final choice of materials in stores | ||
| + | |April||" | ||
| + | |April| |Evaluating marketing objectives part of marketing plan | Sander| | ||
| + | |April||The rest of the marketing plan | Adam| | ||
| + | |April||Introduction | ||
| + | |April||State of the Art | Sander | | ||
| + | |April||Glossary | ||
| + | |April||Team members allocation|Joanna| | ||
| + | |April||Task allocation and work plan | Aleksandra | | ||
| + | |April||Eco-eficiency Measures for Sustainibility|Aleksandra| | ||
| + | |April||Cover | ||
| + | |April||Interim report- structure and graphic | ||
| + | |April||Mid-term presentation| Joanna | | ||
| + | |May, June||PLC programming | ||
| + | |April, May, | ||
| + | |May, June||Build the system | ||
| + | |May, June||Final tests| Joanna | | ||
| + | |April||Logo design | ||
| + | |May, June||Video | Adam | | ||
| + | |May||Functionalities | ||
| + | |May, June||Paper | ||
| + | |May, June||Poster | ||
| + | |May, June||Simulation | ||
| + | |May, June||Project development| Adam, Aleksandra, Joanna and Sander| | ||
| + | |June||Bibliography| Sander | | ||
| + | |May||Conclusions| Joanna | | ||
| + | |May||Abstract | ||
| + | |June||Final presentation | Joanna, Aleksandra, Adam, Sander | | ||